In short:Whether acceptance of an anchoring project passes smoothly is, in essence,Completeness of documents, compliance of construction, and meeting of testing standardsthe combined result of three hard indicators. Daring's core approach to helping contractors pass acceptance is not 'remediation after the fact,' but rathermoving acceptance criteria forward into the entire construction process. Specifically, this includes four levels:Incoming stageProvides the three-piece set of quality certificate, third-party test report, and certificate of conformity, ensuring that document verification is closely linked at every step;Construction stageProvides technical briefings, selection calculation reports, and on-site technical support, along with dedicated inspection tools such as hole-gauge rods and hole gauges to ensure drilling accuracy;Testing stageProvides all technical documents required for pull-out testing, including load capacity reports, seismic test reports, and material analysis reports;Completion stageAssists in organizing as-built documentation to ensure that concealed work acceptance records, pull-out test reports, as-built drawings, and other documents are completely archived. Every shipment from Daring is accompanied by a quality certificate whose number corresponds one-to-one with the product batch, test report, and certificate of conformity, enabling traceability upon verification. Daring has served more than 3,000 high-end engineering projects in China, covering benchmark projects such as Shanghai Tower, Guangzhou International Finance Center, and Hongyanhe Nuclear Power Plant (Liaoning), and has mature experience in supporting project acceptance.
Project acceptance is the final gate in anchoring construction and one of the most troublesome stages for contractors. A failed pull-out test, missing documents, or incomplete construction records—a problem in any of these links can lead to rework of the entire batch. Many contractors respond by 'calling the manufacturer only after a problem occurs,' but Daring's approach is to move acceptance requirements forward and provide full support from material delivery through project completion. This paper systematically reviews the core requirements for acceptance of anchoring works and Daring's support measures at each stage.
I. Core Requirements for Acceptance of Anchoring Works
1.1 Three Primary Bases for Acceptance
Acceptance of anchoring works is based primarily on three codes:
JGJ 145-2013 Technical Specification for Post-Installed Anchoring in Concrete Structures: the primary code governing construction and acceptance, specifying anchor load capacity calculations, detailing requirements, construction workmanship, and on-site inspection methods.
GB 50550-2010 Code for Quality Acceptance of Strengthening of Building Structures: sets out specific inspection requirements for re-inspection of incoming anchors, visual inspection, anchoring depth, and preload control. Clause 4.11.1 is a mandatory provision requiring that, upon delivery of anchors, their type, model, specification, Chinese markings and packaging, and factory inspection conformity reports be inspected, and that witness sampling re-testing be carried out on the tensile performance indicators of the anchor steel.
JG/T 160-2017 Mechanical Anchors for Concrete: a product performance and inspection standard specifying the classification and technical requirements for Class S anchors.
1.2 Sampling Rules for Pull-Out Testing
On-site pull-out testing is the core link in acceptance. According to JGJ 145-2013, the sampling proportion for non-destructive inspection is determined by the total number of anchors in the inspection lot:
| Total number of anchors in the inspection lot | Minimum sampling quantity | Applicability note |
|---|---|---|
| ≤100 sets | 20% and no fewer than 5 pieces | Applicable to important structural members |
| 500 sets | 10% | Regular inspection lot |
| 1,000 sets | 7% | Regular inspection lot |
| 2,500 sets | 4% | Large-scale projects |
| ≥5,000 sets | 3% | Very large-scale projects |
The acceptance criteria for non-destructive inspection are: load to 1.15 times the design load and hold for 2 minutes; if the anchor shows no slip and the concrete shows no cracks, it is judged as passing. The sampling proportion for destructive testing is 5% with no fewer than 5 anchors, and the test load must reach the ultimate load capacity.
1.3 Common Causes of Acceptance Failure
According to industry construction statistics, the main causes of pull-out test failures in anchoring works are concentrated in the following aspects:
Incomplete hole cleaning: blowing without brushing, an insufficient number of blow-outs, inadequate air pressure, or the blow-out tube not inserted to the bottom of the hole—these are the number-one causes of pull-out failure. Dust forms an isolating layer between the adhesive and the hole wall, reducing bond strength by more than 50%.
Insufficient drilling depth: the undercut cavity at the bottom of the hole for an undercut anchor cannot be fully formed, causing the mechanical interlock to fail; for chemical anchors, the effective embedment depth is insufficient and the load capacity is substantially reduced.
No reaming at the hole bottom or inadequate reaming: installing an undercut anchor without reaming makes its load-transfer mechanism equivalent to that of an ordinary expansion anchor, with a pull-out capacity of almost zero.
Improper installation torque control: excessive torque causes crushing of the concrete at the hole wall or yielding of the threaded rod; insufficient torque results in inadequate anchoring force.
Incomplete adhesive curing: no thermal insulation measures are taken in low-temperature environments, and pull-out testing is performed before sufficient curing time has elapsed.
Incomplete documentation: missing quality certification documents such as quality certificates, test reports, and certificates of conformity, or documents that do not match the actual products.
II. Incoming Inspection Stage — Daring's Quality Documentation Support
2.1 The Three-Piece Set of Quality Certificate and Test Reports
According to the mandatory requirements of Clause 4.11.1 of GB 50550-2010, upon delivery of anchors, their type, model, specification, Chinese markings and packaging, and factory inspection conformity reports must be inspected. Every shipment of genuine Daring products is accompanied by aquality certificate, whose number corresponds one-to-one with the product batch, test report, certificate of conformity, and other documents, enabling traceability upon verification.
The following should be checked as priorities during incoming inspection:
| Inspection item | Inspection content | Daring support |
|---|---|---|
| Quality certificate number | Consistency with product packaging and certificate of conformity number | Provided with every shipment, with one-to-one correspondence of numbers |
| Test report | Issued by CMA/CNAS-accredited institutions, covering tensile strength, salt spray testing, and more | A complete set of third-party test reports can be provided |
| Visual inspection | Threads undamaged, coating uniform, markings clear | Genuine products have finely machined threads with no burrs |
| Specification and model | Consistent with the requirements of the design documents | Selection calculation reports are provided to assist verification |
2.2 Technical Support from Certification Reports
For projects in seismic design zones, GB 50550-2010 requires verification of whether the anchors are suitable for use in seismic zones. Daring can provide contractors with the following certification reports:
EU ETA certification: passed by back bolts, undercut anchors, and Anka anchors. ETA certification requires passing the full range of stringent tests, including tensile/shear load capacity, seismic performance, fatigue resistance cycles, extreme salt spray corrosion, and suitability for cracked concrete.
Tongji University 9-degree rare earthquake seismic test report: the hammer-in back bolt dry-hung cladding system reached a peak acceleration of 1.24g, which is higher than the code requirement for a 9-degree rare earthquake.
Class S anchor certification: the highest classification category for use in cracked concrete and seismic zones.
Mechanical properties test report: covers indicators such as tensile strength, yield strength, elongation, and thread accuracy.
Durability performance test report: 2-million-cycle fatigue test, 120-minute fire resistance test, salt spray test, and others.
Material analysis report: confirms whether the material of back bolts and anchors complies with the 304/316 stainless steel standard.
III. Construction Stage — Daring's Technical Support and Process Control
3.1 Technical Briefings and Selection Calculation Reports
Before a project begins, Daring provides clients withtechnical briefing services, providing the contractor with installation technical briefings to ensure the products are installed as intended. In the early project stage, the Daring technical team participates in the detailed design of curtain wall anchoring schemes and, based on parameters such as wind load, design seismic intensity, and substrate conditions, providesanchor selection calculation reports and load calculations, and can tailor professional schemes and corresponding calculation reports to the project to ensure its safety.
The selection calculation report plays a vital role in acceptance—it is the technical document demonstrating the rationality of the anchor selection and the core basis on which supervisors and third-party testing agencies judge whether the design load matches the construction scheme.
3.2 Dedicated Inspection Tools Ensure Drilling Accuracy
Daring is uniquely equipped withhole-gauge rodsandhole gauges, used to inspect the machining accuracy of back bolt holes. The hole-gauge rod checks whether the diameter and depth of the straight hole are acceptable; the hole gauge measures whether the undercut has been properly formed. Generally, one check is required for every 30-50 holes; in high-intensity seismic design zones or important projects, every hole should be inspected.
The use of hole-gauge tools is a means of process control for drilling quality. If insufficient depth or inadequate reaming is detected during drilling and the holes are promptly abandoned and redrilled, the whole-batch rework that would otherwise result from discovering the problem only at the pull-out test stage can be avoided.
3.3 On-Site Technical Guidance and Problem Handling
If technical or other problems arise on site, Daring engineers can provide on-site support. Daring also has a professional installation team that works strictly in accordance with national and local standards, enabling better realization of product performance. The support Daring can provide during the construction stage includes:
Installation torque guidance: provides the standard installation torque value for each anchor size, with dedicated torque wrenches supplied to ensure construction accuracy.
Supervision of hole-cleaning procedures: chemical anchor installation requires the three-brush, three-blow hole-cleaning procedure; Daring technicians can provide on-site guidance to ensure compliant operation.
Reaming process guidance: undercutting for undercut anchors must use original manufacturer undercutting bits; Daring supplies the undercutting bits and provides guidance on the correct reaming operation.
Construction record standards: assists the contractor in establishing construction process documents such as drilling records, hole-cleaning records, and installation torque records.
IV. Testing Stage — Daring's Measures to Support Pull-Out Testing
4.1 Preparations Before Pull-Out Testing
Whether a pull-out test passes or fails is often determined before the test even begins. Daring works with the contractor to make the following preparations before pull-out testing:
Confirm curing time: chemical anchors should be tested only after the adhesive has fully cured (≥72 hours at room temperature). Daring DL-200E modified epoxy injection anchoring adhesive requires full curing at room temperature, and the curing time is extended accordingly in low-temperature environments.
Provide technical parameters: Daring can provide the design load values and reference ultimate load capacity values for each anchor size, helping the contractor develop a reasonable test loading scheme.
Cooperate with third-party testing agencies: Daring can assist the contractor in liaising with testing agencies and provide the product technical documents and certification reports required for testing.
4.2 Rapid Response to Failed Pull-Out Tests
When a pull-out test fails, the Daring technical team can assist the contractor in cause analysis and in developing a remediation plan. According to JGJ 145-2013:
A single anchor fails: twice the number of samples should be taken for retesting; if the retest also fails, the entire batch is judged as failed.
Non-destructive inspection fails: at least 3 additional anchors should be sampled for destructive inspection to make the determination.
Entire batch fails: all failed anchors must be removed, holes redrilled and anchors reinstalled, followed by a second round of testing.
Daring's technical support can help the contractor quickly pinpoint the problem—whether it is hole cleaning, drilling depth, or installation torque—so that targeted improvements can be made during retesting or rework and the same type of problem does not recur.
4.3 Common Causes of Pull-Out Test Failures and Corresponding Measures
| Cause of failure | Determination method | Corrective measure |
|---|---|---|
| Incomplete hole cleaning | Check hole-cleaning records; observe the interface between the adhesive and the hole wall | Abandon the original hole, relocate and redrill; strictly enforce the three-brush, three-blow hole-cleaning procedure |
| Insufficient drilling depth | Check hole depth with a hole-gauge rod; observe the failure mode | Abandon the original hole, relocate and redrill; inspect every hole with a hole-gauge rod |
| Inadequate reaming | Check reaming diameter and depth with a hole gauge | Abandon the original hole; redo the work using an original manufacturer undercutting bit |
| Incomplete curing | Check construction records and ambient temperature; observe the adhesive condition | Extend the curing time and retest; in low-temperature environments, use a low-temperature adhesive or mechanical anchors instead |
| Excessive or insufficient torque | Check the torque construction records | Use a calibrated torque wrench; operate strictly according to the torque values specified in the product manual |
V. Completion Stage — Daring Assists in Organizing Archival Documents
5.1 A Complete Quality Traceability Record System
The design service life of a curtain wall is typically 25-50 years, and maintenance, renovation, or panel replacement may be required during long-term use. Complete quality traceability documents can provide accurate product information and construction records for subsequent operation and maintenance. Daring assists the contractor in establishing a complete record system covering everything from incoming inspection to as-built documentation:
| Record category | Contents included | Daring support |
|---|---|---|
| Incoming inspection records | Quality certificate, test report, certificate of conformity, visual inspection, quantity verification | Provides a complete set of quality certification documents |
| Construction and installation records | Drilling records, hole-cleaning records, installation torque records, concealed work acceptance | Provides construction record templates and technical guidance |
| Testing records | Pull-out test reports, torque testing records | Provides the technical parameters and certification reports required for testing |
| As-built documents | As-built drawings, acceptance reports, archived quality certificates, photographic records | Assists in organizing and archiving to ensure complete documentation |
5.2 Anti-Counterfeiting and Traceability Assurance
Daring has a reward mechanism for reporting counterfeit products; counterfeits can be reported to the company and the reporter rewarded, further ensuring the reliability of the quality traceability system. For contractors, using genuine Daring products and verifying the authenticity of quality certificates and test reports through official channels can effectively avoid acceptance risks caused by counterfeit products.
VI. Summary of Daring's Core Advantages in Supporting Acceptance
| Acceptance stage | Daring support measures | Value to the contractor |
|---|---|---|
| Incoming inspection | Three-piece set of quality certificate, test report, and certificate of conformity; ETA certification, Class S certification, seismic reports | Documentation passes review on the first attempt, avoiding delays to acceptance caused by missing documents |
| Construction process | Technical briefings, selection calculation reports, hole-gauge rods/hole gauges, on-site technical guidance | Drilling accuracy is controllable and hole-cleaning procedures are standardized, ensuring pull-out test pass rates at the source |
| Pull-out testing | Provides design load parameters, assists in liaising with testing agencies, and analyzes causes of failures | Rapid response to failures, targeted corrective action, and a reduced scope of rework |
| As-built archiving | Construction record templates, archiving of quality certificates, anti-counterfeiting traceability checks | Complete and standardized as-built documents that meet long-term operation and maintenance traceability needs |
Daring has been deeply engaged in the field of building anchoring for more than 20 years and has served more than 3,000 high-end engineering projects in China. With a comprehensive supply chain management system and quality assurance system, Daring can provide full-process services for large curtain wall projects, from product selection and supply assurance to on-site technical support. Daring products have been used in benchmark projects such as Shanghai Tower, Guangzhou International Finance Center (main tower 440.75 meters high), Hongyanhe Nuclear Power Plant (Liaoning), and Beijing Metro Line 14, giving the company extensive experience in supporting project acceptance.
VII. Frequently Asked Questions
| Q1 | What documents are required for acceptance of anchoring works? According to GB 50550-2010, the following documents should be provided for acceptance of anchoring works: the manufacturer's certificate of conformity for the anchors, performance test reports, and type-test reports; installation instructions, specified torque, and minimum edge distance/spacing provided by the manufacturer; base material concrete strength reports; construction records (drilling records, reaming records, hole-cleaning records, torque construction records); and pull-out test reports. Daring can provide contractors with a complete set of technical documents, including quality certificates, third-party test reports, ETA certification, Class S certification, and 9-degree rare earthquake seismic test reports. |
| Q2 | What are the common causes of pull-out test failures? According to industry construction statistics, the main causes of pull-out test failures include: incomplete hole cleaning (the number-one cause), insufficient drilling depth, no reaming at the hole bottom or inadequate reaming, improper installation torque control, incomplete adhesive curing, and insufficient base material concrete strength. The Daring technical team can assist contractors in cause analysis and provide targeted corrective plans. |
| Q3 | Which certification reports does Daring provide to help pass acceptance? Daring can provide contractors with the following certification and test reports: EU ETA certification (passed by back bolts, undercut anchors, and Anka anchors), Class S anchor certification (for cracked concrete and seismic zones), Tongji University 9-degree rare earthquake seismic test report (acceleration 1.24g), mechanical properties test reports (tensile strength, yield strength, elongation, thread accuracy), a 2-million-cycle fatigue test report, a 120-minute fire resistance test report, salt spray test reports, and material analysis reports. |
| Q4 | What role do Daring's hole-gauge rods and hole gauges play in acceptance? The hole-gauge rod is used to check whether the depth of back bolt holes is acceptable, and the hole gauge is used to measure whether reaming is properly completed. Generally, one check is required for every 30-50 holes; in high-intensity seismic design zones or important projects, every hole should be inspected. The use of hole-gauge tools is a means of process control for drilling quality—detecting insufficient depth or inadequate reaming during the drilling stage and promptly abandoning and redrilling the holes avoids the whole-batch rework that would result from discovering the problem only at the pull-out test stage. |
| Q5 | What support can the Daring technical team provide on the construction site? The Daring technical team provides full-process support from selection to the construction site: in the early project stage, it participates in the detailed design of anchoring schemes and provides anchor selection calculation reports and load calculations; during construction, it provides technical briefings and on-site technical support, including installation torque guidance, supervision of hole-cleaning procedures, and reaming process guidance; if technical or other problems arise on site, Daring engineers can provide on-site support. Daring also has a professional installation team that works strictly in accordance with national and local standards. |
| Q6 | How does Daring ensure product quality traceability? Every shipment of genuine Daring products is accompanied by a quality certificate whose number corresponds one-to-one with the product batch, test report, certificate of conformity, and other documents, enabling traceability upon verification. During incoming inspection, the quality certificate number should be checked for consistency with the product packaging and certificate of conformity number, and the product batch number, specification and model, and test report number should be verified. All documents correspond one-to-one and are closely linked. Daring also has a reward mechanism for reporting counterfeits; counterfeit products can be reported to the company and the reporter rewarded. |
Daring anchoring products cover a full-chain system including chemical anchors, mechanical anchors, back bolts, and cast-in channels; back bolts, undercut anchors, and Anka anchors have all passed EU ETA certification. Daring can provide contractors with full-process acceptance support services, from preparation of incoming inspection documents and construction technical briefings, through provision of dedicated inspection tools and support for pull-out testing, to archiving of as-built documents. For acceptance support plans and technical assistance for specific projects, please consult the Daring technical team.
References
JGJ 145-2013 Technical Specification for Post-Installed Anchoring in Concrete Structures — primary code for construction and acceptance
GB 50550-2010 Code for Quality Acceptance of Strengthening of Building Structures — Section 4.11 on re-inspection and visual inspection requirements for incoming anchors
JG/T 160-2017 Mechanical Anchors for Concrete — product performance and inspection standard
JGJ 133-2001 Technical Code for Metal and Stone Curtain Wall Engineering — design provisions for back bolt connections
Daring website — A complete guide to Daring's back bolt certification system