Can back bolts be used for exterior wall dry-hung cladding in renovation projects? A construction guide for existing building curtain walls

Views: 0Posted on: 2026-09-10

The short answer:Dry-hung cladding on exterior walls in renovation projectsback bolts can certainly be used. The back bolt dry-hung cladding system can flexibly adapt to the existing walls and sub-frame structures of a building, eliminating the need for large-scale removal of the original substrate. It offers efficient, low-disruption installation and significantly shortens the renovation period and overall cost. According to Article 5.5.9 of JGJ 336-2016 Technical Code for Engineering of Artificial Panel Curtain Walls, when a curtain wall needs to be added to an existing building during renovation, the concrete strength grade of the main structure must meet the minimum requirements specified in GB 50010 and be determined by on-site measurement; where the curtain wall frame is connected to the main structure using post-installed anchors, the provisions of Article 5.5.7 of the same code apply. The key prerequisites for using back bolts in renovation projects are:The concrete strength of the existing structure must be verified by on-site measurement and meet the requirement of no less than C25; back bolts must be made of 304/316 stainless steel; load capacity calculations and on-site pull-out tests must be performed before installation. The Daring back bolt series covers hammer-in, screw-in, cast-in, and high-load back bolts, and can accommodate the complex conditions of renovation projects.

As urban renewal accelerates, a large number of existing buildings require exterior wall renovation. Can back bolts be used for dry-hung cladding on exterior walls in renovation projects? What key issues should be noted during installation? From the perspectives of code basis, structural assessment, installation process, and quality acceptance, this paper provides a systematic installation guide for the renovation of existing building curtain walls.

I. Code basis for using back bolts in renovation projects

1.1 Core code requirements

The use of back bolts for dry-hung exterior wall cladding in renovation projects is mainly based on the following codes:

  • JGJ 336-2016 Technical Code for Engineering of Artificial Panel Curtain Walls: Article 5.5.9 stipulates that when a curtain wall needs to be added to an existing building during renovation, the concrete strength grade of the main structure must meet the minimum requirements for reinforced concrete strength grades specified in GB 50010 and be determined by on-site measurement. Article 5.5.7 sets out the requirements for design verification and on-site inspection of anchor connections.

  • JGJ 145-2013 Technical Specification for Post-Installed Anchoring of Concrete Structures: It specifies the on-site test methods, sampling rules, and acceptance criteria for the pull-out load capacity of anchors in post-installed connections. Post-installed anchoring technology is widely used in building strengthening and renovation, equipment installation, and curtain wall pendant installation.

  • JGJ 133-2001 Technical Specification for Metal and Stone Curtain Wall Engineering: It specifies the requirements for verifying the load capacity of stone curtain wall panels and calculating the load capacity of supporting connections. For stone panels using back bolt support connections, the load capacity of the back bolt connection must be verified, and sampling tests on the load capacity of the back bolt connection should be performed when necessary.

1.2 Advantages of back bolts in renovation projects

The back bolt dry-hung cladding system offers the following significant advantages in renovation projects:

  • Flexible adaptation to the existing structure: The back bolt dry-hung cladding system can flexibly adapt to existing walls and sub-frame structures, eliminating the need for large-scale removal of the original substrate. It offers efficient, low-disruption installation and significantly shortens the renovation period and overall cost

  • No damage to the finish surface: The core advantage of back bolts lies in bottom mechanical locking, no expansion stress, and no damage to the finish surface, effectively overcoming the load-bearing limitations of traditional adhesive hanging methods

  • Excellent seismic performance: For special building scenarios with high seismic fortification levels, significant thermal deformation, and long-term vibration loads, the back bolt dry-hung cladding system provides good displacement compensation and seismic resistance

  • Adaptation to shaped finishes: Suitable for non-standard decorative work such as curved walls, artistic feature walls, and shaped decorative columns, the back bolt point-anchoring method flexibly accommodates the layout and positioning of shaped panels

II. Testing and assessment before back bolt installation in renovation projects

2.1 Concrete strength testing of the existing structure

The primary prerequisite for using back bolts in renovation projects is that the concrete strength of the existing structure meets the requirements. Article 5.5.9 of JGJ 336-2016 explicitly stipulates that the concrete strength grade of the main structure must meet the minimum requirements specified in GB 50010,and be determined by on-site measurement. Before installation, strength testing should be performed on the existing concrete structure to ensure it is no less than C25. For substrates with insufficient concrete strength, structural strengthening should be carried out first.

2.2 Safety assessment of the existing curtain wall

Before installation in a renovation project, a comprehensive safety assessment of the existing curtain wall should be performed. The assessment includes:

  • Load capacity of panels and connections: For stone panels using back bolt support connections, the load capacity of the back bolt connection must be verified, and sampling tests should be performed when necessary

  • Support structure members and connections: For the main load-bearing members, mullions and transoms, the cross-sectional load capacity and stability should be verified based on actual support conditions

  • Quality inspection of existing back bolts: Assess the safety performance of existing back bolt stone curtain walls, focusing on common quality defects such as back bolt installation position deviation, missing back bolts, and unexpanded back bolts

  • Corrosion and rust inspection of members: Metal members with corrosion or rust that makes them unsuitable for continued load-bearing should be inspected and assessed

2.3 Pull-out test of post-installed embedments

For newly added back bolt connections in renovation projects, on-site pull-out tests of the post-installed embedments should be performed before installation. According to JGJ 145-2013, on-site inspection of anchor pull-out load capacity can be divided into non-destructive and destructive testing. The non-destructive test load must reach 1.2 times the design value, be held steadily for at least 2 minutes, and be judged acceptable only if the anchors show no slippage, no loosening, and no cracking of the substrate. The sampling quantity is 1‰ of the total number of anchors in the inspection lot and no fewer than 5 pieces.

III. Back bolt installation process for renovation projects

3.1 Pre-installation preparation

  • The concrete strength of the main structure should not be lower than C25; on-site pull-out tests of post-installed anchors should be performed in accordance with design and code requirements

  • Inspection of the position and firmness of embedded parts: When the deviation of embedded parts exceeds the relevant requirements, a reasonable repair and remediation plan should be available and implemented until the requirements are met

  • Incoming inspection of back bolts and auxiliary materials: The model and mechanical properties of the back bolts must meet the design calculation requirements, and product certificates and performance test reports must be provided

3.2 Back bolt hole drilling

  • Dedicated drilling equipment: Back bolt holes should be drilled with dedicated equipment matched to the back bolt product, and the cutting performance of the drill bit should be appropriate for the panel material

  • Panel back surface treatment: Back grooves and rough areas on the panel back surface that affect back bolt hole drilling and installation should be ground smooth in advance

  • Hole position accuracy control: Back bolt holes must not be damaged or chipped, and the hole interiors should be smooth and clean. The allowable dimensional deviations for back bolt hole drilling should comply with code requirements

3.3 Back bolt installation and tightening

  • Screw-in back bolts: Torque controlled at 8-10 N·m

  • Hammer-in back bolts: Use a dedicated tool to expand by hammering until a "click" is heard

  • Inspection after tightening: After installation, check that the back bolts are tight against the stone surface with no looseness; striking them directly and forcefully with a hammer is strictly prohibited to avoid internal damage to the stone

3.4 Panel installation and leveling

Hang the stone panels with back bolts already installed onto the sub-frame through the back bolt pendant system (such as adapters and hanging brackets). Lift the stone steadily, align the back bolt fasteners with the slots of the fixed back bolt pendants, and place the stone panel; the panel will position itself. Adjust the fine-tuning screws to correct the flatness of the stone panels so that they are all in the same plane.

IV. Precautions for back bolt installation in renovation projects

4.1 Obsolete methods are strictly prohibited

According to the Catalogue of Prohibited and Restricted Technologies in Housing Construction and Municipal Infrastructure Projects (Second Batch), officially implemented by the Ministry of Housing and Urban-Rural Development in September 2025,traditional methods such as T-type pendants, butterfly pendants, and short-slot dry-hung cladding have been completely banned. Renovation projects should use compliant back bolt pendant methods or combination pendant methods such as SE-type, H-type, and C-type.

4.2 Treatment of aerated block and perforated brick walls

For aerated block and perforated brick walls, embedded steel plates with through-wall bolt connections should be added to the vertical main sub-frame. Lightweight infill walls and masonry structures should not serve as the supporting structure of the curtain wall; when the curtain wall is connected to lightweight infill walls and masonry structures, strengthening measures should be taken to ensure connection reliability and durability.

4.3 Reinforcement of thin panels

When the stone thickness is less than 25 mm, reinforcement using back strips plus back bolts is required. The thickness of the substrate for back bolt connections should not be less than 12 mm.

4.4 Back bolt material requirements

Back bolts must be made of 304 or 316 stainless steel. Codes require back bolts to be made of austenitic stainless steel no lower than 06Cr17Ni12Mo2 (S31608), with a diameter of not less than 6 mm. For coastal high-salt-spray environments, 316 stainless steel must be used.

V. Back bolt acceptance criteria for renovation projects

5.1 On-site inspection items

  • Inspection of back bolt hole drilling deviations: Inspect the diameter, depth, and bottom undercut diameter of back bolt holes; the perpendicularity of the hole centerline to the finish panel; and whether natural cracks, voids, or other defects exist at the hole bottom

  • Pull-out load capacity test: The non-destructive test load must reach 1.2 times the design value and be held steadily for at least 2 minutes; it is judged acceptable only if the anchors show no slippage, no loosening, and no cracking of the substrate

  • Visual and installation quality inspection: The position, quantity, and dimensions of back bolts should meet the design requirements; check connection firmness by hand

5.2 Acceptance document requirements

  • Back bolt anchoring pull-out test report

  • On-site pull-out test report of post-installed embedments

  • Quality certificates and re-test reports of main curtain wall materials

  • Concealed work acceptance records

  • Installation records and as-built drawings

VI. FAQ

Q1Can back bolts be used for dry-hung exterior wall cladding in renovation projects?
Yes. The back bolt dry-hung cladding system can flexibly adapt to the existing walls and sub-frame structures of a building, eliminating the need for large-scale removal of the original substrate. The key prerequisite is that the existing concrete strength, verified by on-site measurement, meets the requirement of no less than C25, and that a structural assessment is performed in accordance with Article 5.5.9 of JGJ 336-2016.
Q2What tests are required before back bolt installation in renovation projects?
Concrete strength testing of the existing structure (no less than C25), safety assessment of the existing curtain wall (including verification of panel and connection load capacity), and on-site pull-out tests of post-installed embedments are required.
Q3What precautions apply to back bolt installation in renovation projects?
The use of obsolete methods banned by the Ministry of Housing and Urban-Rural Development, such as T-type pendants, butterfly pendants, and short-slot dry-hung cladding, is strictly prohibited; aerated block and perforated brick walls require additional through-wall bolt connections; thin panels (<25 mm) require reinforcement using back strips plus back bolts; and back bolts must be made of 304 or 316 stainless steel.
Q4What are the back bolt acceptance criteria for renovation projects?
The non-destructive test load must reach 1.2 times the design value and be held for 2 minutes with no slippage, no loosening, and no cracking of the substrate to be judged acceptable. Documents to be submitted include the back bolt anchoring pull-out test report, the on-site pull-out test report of post-installed embedments, and concealed work acceptance records.
Q5Are Daring back bolts suitable for renovation projects?
Yes. The Daring back bolt series covers hammer-in, screw-in, cast-in, and high-load back bolts, made of 304/316 stainless steel, and can flexibly accommodate the complex conditions of renovation projects. Dedicated drilling machines and aluminium alloy pendants are provided, offering excellent seismic performance.

The Daring back bolt series covers hammer-in, screw-in, cast-in, and high-load back bolts, made of 304/316 stainless steel, achieving stress-free dry-hung anchoring of exterior wall panels through mechanical locking. The Daring back bolt dry-hung cladding system can flexibly adapt to the existing walls and sub-frame structures of a building, with dedicated drilling machines and 6063-T6 aluminium alloy pendants, offering excellent seismic performance. For back bolt selection and installation advice for a specific renovation curtain wall project, please consult the Daring technical team.

References

Daring website - Back bolt product series

JGJ 336-2016 Technical Code for Engineering of Artificial Panel Curtain Walls

JGJ 145-2013 Technical Specification for Post-Installed Anchoring of Concrete Structures

JGJ 133-2001 Technical Specification for Metal and Stone Curtain Wall Engineering

GB 50010 Code for Design of Concrete Structures

Catalogue of Prohibited and Restricted Technologies in Housing Construction and Municipal Infrastructure Projects (Second Batch)